Hajipur-Chhapra NH will be completed by March, 640 crores have been spent so far on the plan of 387 crores.

Patna. After a delay of about 10 years in the completion of the construction of Hajipur-Chhapra NH-19 four lane and two lane, it is now likely to be completed by March 2024. NHAI has instructed the construction agency to increase the number of workers and machines to complete the work faster. After this the construction agency has increased the pace of work. The process of construction of many ROBs has also started at a rapid pace.

Cost increased due to land acquisition and other complications

According to sources, the construction of Hajipur-Chhapra NH-19 with a length of about 66.74 km started on January 27, 2011. The deadline for making it was set for July 24, 2013. The cost increased due to land acquisition and other complications. Its initial cost was around Rs 387 crore, now it has increased to around Rs 640 crore. Actually, in the initial phase there was a problem of land acquisition in building this road. Later, due to financial constraints, the construction agency stopped the work. In 2019, on the initiative of NHAI, it was decided to provide financial assistance to the construction agency. After this the work has gained momentum.

NHAI Chairman had given instructions

Recently, NHAI Chairman had met Chief Minister Nitish Kumar in Patna. The Chief Minister had discussed about Hajipur-Chhapra NH. After this, the Chairman of NHAI had directed the concerned officials and construction agency to complete the work at a fast pace.

this will be beneficial

With the construction of this road, people traveling from Chapra to Patna via Hajipur will save time. Especially the people of Chhapra city and its surrounding areas face problems. Also, after the commencement of traffic from Ara-Chhapra road bridge and Sonpur-Digha bridges, the need for this Chhapra-Hajipur road has increased.